PMI PMP Practice Test - Questions Answers, Page 129

List of questions
Question 1281

A new team member is assigned to a team that consistently delivers each iteration. The new team member does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?
Question 1282

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the required IT system. What should the project manager do?
Question 1283

A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.
How should the project manager build a cohesive, high-performing team?
Question 1284

A project manager is leading a project at a contracting company, and the project team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.
What should the project manager do to avoid this situation in the future?
Question 1285

A project team delivered a critical deliverable to the customer. The customer complained that the maintenance manual was not included.
What should the project manager do next?
Question 1286

A company is moving its headquarters to another city. The project manager responsible for the assignment has been using a predictive approach during the transition. However, the information systems will be migrated using an agile approach. The project manager needs to decide which kind of contract to sign with the vendor responsible for migrating the systems. The project manager is concerned about controlling finances while delivering results.
How should the project manager address this situation?
Question 1287

A leader from project B consistently reaches out to a team member in project A for assistance.
What should project A's project manager do?
Question 1288

A risk was identified at the beginning of a project, and a response plan was established.
Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan.
What should the project manager do?
Question 1289

The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck.
The team has researched a tool that could resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?
Question 1290

A project manager has taken over a project that has been without a project manager for the last couple of weeks. The team is feeling lost and there are a few team members who are confused about the next steps and the final outcome of the project.
What should the new project manager do?
Question