PMI PMP Practice Test - Questions Answers, Page 131
List of questions
Question 1301
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects start going to market, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints. This request does not match the project manager's expectation, since a program manager is overseeing the remaining work.
How should the project manager approach the situation?
Question 1302
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain feedback from on project deliverables. What should the project manager do?
Question 1303
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have most likely caused this communication breakdown?
Question 1304
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.
What should the project manager do?
Question 1305
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In a product development project, the project manager is constantly receiving complaints from stakeholders about functionalities being delivered, but not required by the business departments.
The project sponsor wants to know if the project resources are being used effectively.
What should the project manager have done to avoid delivering work that is not adding value to the business?
Question 1306
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
The project leader for an agile team has discovered that a certain team member has been struggling with an impediment that is hindering the team's progress. The project is now at risk of completing later than expected.
What should the project leader do?
Question 1307
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is working on a project using a hybrid approach. The project is scheduled to be completed in three more sprints. One of the team members notifies the project manager that they are leaving the company, which was approved by their functional manager.
What should the project manager do first in this situation?
Question 1308
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much experience in development.
What should the project manager do?
Question 1309
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three.)
Question 1310
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
In a project steering committee meeting, a few stakeholders raise concerns that the project manager's report shows that the outcome of the project is already in the market while the project is still in development. The project manager explains that the project is being delivered in sprints and involves different releases.
What should the project manager do to avoid a reoccurrence of this scenario?
Question