ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 133

List of questions

Question 1321

Report
Export
Collapse

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?

Become a Premium Member for full access
  Unlock Premium Member

Question 1322

Report
Export
Collapse

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 1323

Report
Export
Collapse

In a fixed time and budget project, the customer wants the development of a core component to be based on agile practices, as the final scope of the requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.

Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 1324

Report
Export
Collapse

A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1325

Report
Export
Collapse

A team member is openly criticized by others during a standup meeting for failing to complete yesterday's tasks. What should the agile coach do first to address the situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 1326

Report
Export
Collapse

A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1327

Report
Export
Collapse

As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?

Become a Premium Member for full access
  Unlock Premium Member

Question 1328

Report
Export
Collapse

A project manager is leading an integration project for a retail company. The project demands a lot of time from the stakeholders to make important business decisions. The project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this project?

Become a Premium Member for full access
  Unlock Premium Member

Question 1329

Report
Export
Collapse

A recently concluded quality audit failed and came back with multiple action items. A newly appointed project manager is reviewing the project status with the team. New stakeholders have been identified, and new audit resources may have to be added to the project.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1330

Report
Export
Collapse

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions