Question 1351

Report Export Collapse

A project manager has been assigned to a high-visibility project that has been identified as having medium complexity, based on previous similar projects. The project needs to be delivered to the customer as a ready-to-use product.

Based on this scenario, what should the project manager focus on throughout the project life cycle?

Become a Premium Member for full access
  Unlock Premium Member

Question 1352

Report Export Collapse

An organization imports many of the materials for a product build. Due to global shipping delays, some of the essential materials have yet to arrive, resulting in the inability to finish building the product for the upcoming release. The project manager is meeting with stakeholders to discuss options.

What should the project manager recommend?

Become a Premium Member for full access
  Unlock Premium Member

Question 1353

Report Export Collapse

During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 1354

Report Export Collapse

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Become a Premium Member for full access
  Unlock Premium Member

Question 1355

Report Export Collapse

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Become a Premium Member for full access
  Unlock Premium Member

Question 1356

Report Export Collapse

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality management plan and there is no reference to this component.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1357

Report Export Collapse

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1358

Report Export Collapse

During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 1359

Report Export Collapse

A lead project manager for an agile project needs to prioritize requirements, define the scope of the initial product, and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 1360

Report Export Collapse

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?