PMI PMP Practice Test - Questions Answers, Page 15
List of questions
Related questions
During the execution phase of a project, a new department has been created in the company.
The manager of this department has requested to be involved in the regular project communications and reporting cycles.
What should the project manager do?
Close to the end of a project, a customer claims that some deliverables have not been met and starts initiating change requests.
What should the project manager do next?
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?
A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?
An agile project is running its third iteration with a duration of 2 weeks. A new operations director, who only has a predictive background, started working at the company. In the first meeting with the project manager, the director demands a weekly project status report.
What should the project manager do?
Several components of an expensive manufacturing project have been returned by the customer.
The customer is complaining that the quality of the components is poor and is concerned that, as a result, their products will be returned due to quality issues. The project manager is certain that quality has been maintained.
How should the project manager communicate with the customer to help assure them that the project has produced quality products?
A company is working on a project to develop an integration of their existing systems. There are known issues in production.
What should the project manager do?
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?
A mid-size capital project has shared resources from the company's contract department. During the execution phase, the project team observed a delay in contracting. After communicating with the contract department, the project manager found the contract team is prioritizing other contracting jobs because they are not part of the project team.
What should the project manager do first in this situation?
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively, among other critical blockers.
What should the project manager do?
Question