PMI PMP Practice Test - Questions Answers, Page 40
List of questions
Question 391

A project manager has been assigned to a project and receives the project charter from the project management office (PMO). The document is very clear about customer requests. During Project Scope Management some requirements seem to be different from the ones specified within the project charter.
What should the project manager do?
Question 392

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories.
In how many iterations should the project manager estimate the story duration?
Question 393

An agile project is running its fifth iteration out of eight. After the last iteration planning the team was informed that there is a new competitor in the market, and it is necessary to move faster to ensure market share is not missed.
What should the project manager do?
Question 394

During the development of a product, the project manager observes conflicts between project stakeholders, resulting in deliverable and output approval delays.
On which area should the project manager focus?
Question 395

During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks.
How should the project manager address this situation?
Question 396

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track.
What will the project manager need to focus on as a result of this decision?
Question 397

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks. The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team.
How should the project manager handle this situation?
Question 398

During daily calls team members share task progress. One team member does not usually communicate many details and has critical tasks to be completed. All team members are located in different countries and critical work is about to start.
Which two options will help the project manager in this situation? (Choose two.)
Question 399

A project manager is implementing a new software system. Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes.
What should the project manager have done at the start of the project to prevent this resistance'?
Question 400

One of a project manager's team members is continuously improving. This team member has been a role model and mentor to others in the organization.
How should the project manager acknowledge this team member's commitment?
Question