PMI PMP Practice Test - Questions Answers, Page 50
List of questions
Related questions
One team member is not as active as the rest of the team during a brainstorming session. The project manager has a separate conversation with the team member and learns that the team member is slightly hearing impaired. The team member appreciates the project manager's concern. The project manager then decides to change the time and room for the meeting to ensure everyone can participate.
What interpersonal skill did the project manager use?
For the purposes of quality assurance, a quality audit was conducted on the processes being used in the project execution plan. One of the nonconformance issues raised by the auditor was that attendance lists for the project risk review meetings were not available.
Why is an attendance list important?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally.
What should the project manager do?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete.
What should the project manager do?
A project manager has a team of shared resources from other projects who are working on a client project. Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time. Competing priorities of the shared resources are delaying delivery of the component.
What should the project manager have done to prevent this delay from happening?
A project manager has been managing a highly complex project. The project manager has ensured that all of the required tasks have been completed. During a recent external audit. The project manager was informed of a heavy penalty being levied on the project for the latest module that was implemented.
What should the project manager have done to ensure that there were no liabilities arising from the recent implementation?
A project manager at a company is considering a high-performing junior member of the organization to be the new project manager for a current project.
What should the project manager do to prepare for a recommendation to senior management?
A project manager is assigned to a project that is in development. As the project manager reviews the project's progress, they find a few tasks that are behind schedule. After investigating, the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager's project.
Which two actions can the project manager take to bring the team back on track? (Choose two.)
A project manager accepts a delivery at the project site but the items are of a poor quality. The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected.
What should the project manager do going forward?
During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1,500 rpm (rate-per-minute) -> warns of max rate allowed
1,400 rpm (rate-per-minute) -> reduces the power and brakes the engine Which of the following statements is correct?
Question