Question 144 - PMP discussion

Report
Export

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

A.
Ask the customer to reduce the backlog to meet the launch date.
Answers
A.
Ask the customer to reduce the backlog to meet the launch date.
B.
Increase the capacity of the team to deliver the completed backlog on time.
Answers
B.
Increase the capacity of the team to deliver the completed backlog on time.
C.
Assist the team in defining a minimum viable product (MVP) by the launch date.
Answers
C.
Assist the team in defining a minimum viable product (MVP) by the launch date.
D.
Schedule a meeting with the stakeholders to review the contingency plan.
Answers
D.
Schedule a meeting with the stakeholders to review the contingency plan.
Suggested answer: C