PMI PMP Practice Test - Questions Answers, Page 115
List of questions
Question 1141
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A virtual team has disagreements about the client's requirements. Although the requirements are written, the language seems ambiguous for some of the team members who are working abroad.
The local team members argue that the language is clear, but that there is a lack of competence from the international team members.
Which two actions should the project manager take? (Choose two.)
Question 1142
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is managing a technical project that requires intensive documentation as part of the key deliverables. In a project review meeting. a key stakeholder reports that the latest documentation provided by the project manager includes a reference to unrelated products.
What should the project manager do?
Question 1143
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
Question 1144
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A client has asked the project manager for the program status report. The project manager sends the report and then realizes that they accidentally included another manager from the client's organization on the email.
What should the project manager do?
Question 1145
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
During a project's closing phase, the project manager identified that the client did not use one particular service. The client then asks the project manager to informally extend the service beyond the contract end date. The contract is clear about the expiration of the service.
How should the project manager address this situation in order to close the project?
Question 1146
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager has been approached by the project sponsor about adding to the project scope. How should the project manager accommodate this request?
Question 1147
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing project. Based on that information, the project manager believes the project should be stopped.
How should the project manager handle the situation?
Question 1148
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is executing a commercial building project. The project manager discovers that the required building permits have not been obtained. Obtaining the permits will delay the project by 1 month and will cost the project US$35,000. The fine associated with continuing to build without the permits is US$1,000 per day.
What should the project manager do first?
Question 1149
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.
Which activity should the project manager undertake?
Question 1150
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project sponsor has requested that the project manager reprioritize the team's tasks to include a feature that is not part of the minimum viable product (MVP) for the project. Although the project sponsor is very keen on the feature, adding it has the potential of causing team burnout and/or delaying the release.
How should the project manager address this situation?
Question