PMI PMP Practice Test - Questions Answers, Page 116
List of questions
Related questions
Due to a recent company merger, a project manager from company B has been assigned to a team that is comprised of team members from company A. At the start of the project, conflicts anise due to a lack of clarity on processes and the project manager's relationship with company B.
What should the project manager do to resolve this conflict?
A project manager has received a new request to integrate more features to a product. The team is fully allocated, and there is no budget to acquire new resources What strategy should the project manager implement to deal with this situation?
A compliance strategy was created during the planning phase of a project. During execution, the project manager left the organization and another project manager was assigned to the team.
What should the project manager do first to ensure the project is compliant?
During project execution, the client requires several changes that will impact the project's duration. The project manager needs to apply fast-tracking techniques to accelerate the schedule, but the team is concerned about working overtime.
What should the project manager do to motivate the team?
A project manager has been running an agile project for 6 months and has been reporting that the project is on track every week. However, on the last week before releasing the final product, the team found a technical impediment that put the project delivery in jeopardy overnight.
What should the project manager have done to prevent this situation?
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.
What should the project manager do next?
A project sponsor has requested a trend analysis of all risks that the project has monitored over the past 12 months. What should the agile project manager do?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
A project manager learns that the performance of a high-performing project team member is deteriorating. This team member is a key member of the project.
Which action should the project manager take to motivate and enhance the project team member's performance?
A project is being planned to deliver a proof of concept to evaluate technology compatibilities.
The business and project stakeholders are having difficulty agreeing on what should be included in the final product.
What should the project manager do?
Question