PMI PMP Practice Test - Questions Answers, Page 37

List of questions

Question 361

Report
Export
Collapse

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments.

What should the project manager suggest that the product owner do next?

Ensure that the impediments are captured and prioritized based upon the highest valued features
Ensure that the impediments are captured and prioritized based upon the highest valued features
Estimate the financial impact of the impediments and request additional funding
Estimate the financial impact of the impediments and request additional funding
Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment
Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment
Capture the impediments and inform management that their assistance is needed in resolving the impediments
Capture the impediments and inform management that their assistance is needed in resolving the impediments
Suggested answer: A
asked 23/09/2024
Jose Castillo
39 questions

Question 362

Report
Export
Collapse

A company was awarded a project in a dangerous location that poses several high-level risks for employees. Help is needed to tram the employees on major safety and health factors. The project is ongoing and uses a hybrid approach. The project will be conducted in multiple sites, with several development iterations running in parallel.

How should the project manager handle this situation?

Allocate and use part of the project's contingency reserves for training purposes
Allocate and use part of the project's contingency reserves for training purposes
Negotiate a contract and form a partnership with a local authority for medical and security support services
Negotiate a contract and form a partnership with a local authority for medical and security support services
Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training
Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training
Hire only local resources who are aware of the territory's hazards, providing employment to the local community
Hire only local resources who are aware of the territory's hazards, providing employment to the local community
Suggested answer: C
asked 23/09/2024
safiqueahmed kazi
37 questions

Question 363

Report
Export
Collapse

A vendor informed the project manager that a critical resource will be on a long leave of absence.

The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.

What should the project manager do next?

Request a replacement resource
Request a replacement resource
Perform a cost-benefit analysis
Perform a cost-benefit analysis
Implement risk responses
Implement risk responses
Perform Integrated Change Control
Perform Integrated Change Control
Suggested answer: D
asked 23/09/2024
Jennifer Okai Addey
36 questions

Question 364

Report
Export
Collapse

A project manager just started managing agile projects. The project manager realizes that due to the lack of a clear definition of project objectives and definition of done (DoD), their colleague's projects have had many difficulties. Sponsors keep asking for more features and the projects have yet to be completed.

What should the project manager do to avoid these issues?

Arrange meetings to ensure every necessary task to complete the project is included in the project management plan
Arrange meetings to ensure every necessary task to complete the project is included in the project management plan
Convince the project sponsor to incorporate quality experts so the product can be tested and accepted as completed
Convince the project sponsor to incorporate quality experts so the product can be tested and accepted as completed
Convince the product owner to approach the team and look for options to find a solution to the problem
Convince the product owner to approach the team and look for options to find a solution to the problem
Schedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project
Schedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project
Suggested answer: D
asked 23/09/2024
Neftali Baez-Feliciano
31 questions

Question 365

Report
Export
Collapse

A member of the board of directors is the sponsor of a project that is important to the organization. This stakeholder has many other priorities and is not currently engaged in the project activities.

How should the stakeholder be engaged in the project?

Keep the stakeholder informed and consult with them based on their needs
Keep the stakeholder informed and consult with them based on their needs
Involve the stakeholder in governance and decision making
Involve the stakeholder in governance and decision making
Consult with the stakeholder and increase their level of interest
Consult with the stakeholder and increase their level of interest
The stakeholder needs to be made aware of the project progress
The stakeholder needs to be made aware of the project progress
Suggested answer: A

Explanation:

Keep the stakeholder informed and consult with them based on their needs is the best approach.

This will ensure that the stakeholder is kept up to date on the project's progress and can provide input or guidance when necessary. It is important to consult with the stakeholder to understand their needs and priorities and to align the project with those as much as possible.

Explanation:

asked 23/09/2024
Andrew Dobie
34 questions

Question 366

Report
Export
Collapse

A marketing team is planning for a multiyear initiative that will include a lot of cross-functional stakeholders. The project manager has been assigned and is now in the project planning phase.

What item(s) should the project manager develop first?

A product backlog and identification of the features to be delivered
A product backlog and identification of the features to be delivered
A business case and scope document
A business case and scope document
A communications management plan that addresses the team's needs
A communications management plan that addresses the team's needs
A risk management plan to incorporate known risks
A risk management plan to incorporate known risks
Suggested answer: C
asked 23/09/2024
Koh Renbin
35 questions

Question 367

Report
Export
Collapse

A key project stakeholder showed interest in the beginning of a complex agile project, but has become less involved as the sprint has progressed due to additional responsibilities. A few sprints later, the key stakeholder rejected a feature deliverable. The team is reworking the rejected deliverable for the next sprint.

What should the project manager have done to avoid this situation?

Involved the key stakeholders in the decision-making process
Involved the key stakeholders in the decision-making process
Customized stakeholder communications based on the stakeholders' needs
Customized stakeholder communications based on the stakeholders' needs
Analyzed the changes in stakeholder attributes
Analyzed the changes in stakeholder attributes
Documented the project vision and objectives
Documented the project vision and objectives
Suggested answer: A
asked 23/09/2024
Wilfried Wagener
36 questions

Question 368

Report
Export
Collapse

As a member of an organizational change management team, a project manager must pass on any changes to the project team. The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change.

What should the project manager do?

Conduct meetings with resistant members to facilitate smooth project implementation
Conduct meetings with resistant members to facilitate smooth project implementation
Meet with the team on a regular basis to ensure they are aware of changes
Meet with the team on a regular basis to ensure they are aware of changes
Influence the team to communicate any changes
Influence the team to communicate any changes
Check with the team members on their willingness to change
Check with the team members on their willingness to change
Suggested answer: B
asked 23/09/2024
HC KONG
42 questions

Question 369

Report
Export
Collapse

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control. The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer.

What should the project manager do?

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve
Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve
Develop the quality management plan, as quality is as equally important as cost and schedule management
Develop the quality management plan, as quality is as equally important as cost and schedule management
Get confirmation from management that the team member has enough experience to build software without quality control
Get confirmation from management that the team member has enough experience to build software without quality control
Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project
Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project
Suggested answer: B
asked 23/09/2024
tho nguyen
37 questions

Question 370

Report
Export
Collapse

A marketing team is developing ideas in order to revamp an existing product. The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch.

On what should the project manager focus?

Ensuring that the team is also focused on the overall change management plan
Ensuring that the team is also focused on the overall change management plan
Determining and aligning performance indicators that will help in assessing successful delivery
Determining and aligning performance indicators that will help in assessing successful delivery
Planning for regular project updates to cover the status of critical deliverables
Planning for regular project updates to cover the status of critical deliverables
Ensuring that the scope management plan is in place to cover all related objectives
Ensuring that the scope management plan is in place to cover all related objectives
Suggested answer: B
asked 23/09/2024
Yogen Trikannad
34 questions