PMI PMP Practice Test - Questions Answers, Page 36
List of questions
Question 351

The customer's project manager changes during the final stage of a project.
How can the project manager avoid a project closure delay?
Question 352

In an industrial plant, the owner has decided to add more capacity to the plant by installing a new machine and updating the software used in production. This capacity enlargement will occur while the plant is still functioning and producing.
The software update will be accomplished using an agile approach in order to minimize risk. The machine procurement, installation, and integration will be accomplished using predictive approaches.
What types of communications will the project manager have to design into the schedule management plan to ensure the project will be on schedule?
Question 353

During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed.
What should the project manager do?
Question 354

During project execution, a conflict occurs between the project manager and one of the team members at every project team meeting. The ongoing conflict is preventing tasks and deliverables from being completed. The project manager contemplates changing their leadership style.
What should the project manager do?
Question 355

A newly formed team has become accustomed to agile practices. The project lead has noticed that while they are performing according to expectations, there is boredom with daily team practices among many of the team members.
What should the project lead do in this situation?
Question 356

A company starts implementing Scrum. About halfway through the first sprint, communication issues develop. Some project team members are not in sync with other team members.
What is the cause for this communication gap?
Explanation:
In Scrum, a sprint is a time-boxed iteration of work during which a specific set of tasks is completed and delivered. During a sprint, daily standup meetings, also known as daily Scrums, are held to provide an opportunity for team members to communicate with each other and coordinate their work.
The purpose of daily standup meetings is to ensure that team members are aware of what each other is working on, identify any issues or obstacles that need to be addressed, and coordinate their efforts to ensure that the tasks for the sprint are completed on time. If daily standup meetings are not held or enforced, it can lead to a communication gap and a lack of coordination among team members, which can negatively impact the progress and success of the sprint.
Explanation:
Question 357

During the course of a project, the project manager's immediate director is communicating directly with the client to approve changes without the project manager's knowledge. This is causing confusion in the project team where the scope is changing in the background, but only being mentioned in project meetings.
How should the project manager handle this?
Question 358

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints. However, the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion.
What are two issues that these actions by the project manager could cause? (Choose two.)
Question 359

A client is structured as a matrix organization for an agile project. The project manager is working on-site with key stakeholders from different parts of the organization.
How should the project manager handle the different stakeholders?
Question 360

A project manager is leading an in-house company project in its very early stages. This current project is similar to another project that ended a year ago.
What should the project manager do to analyze the involved stakeholders?
Question