Question 421

Report Export Collapse

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration. At this point, the project manager learns about a possible change in regulations that would prevent the product launch.

What should the project manager do to realize benefits?

Become a Premium Member for full access
  Unlock Premium Member

Question 422

Report Export Collapse

After a couple of iterations, the project manager decides to present the product to a key stakeholder. The stakeholder's feedback is that the team missed the mark on many features.

What should the project manager do to avoid this in the future?

Become a Premium Member for full access
  Unlock Premium Member

Question 423

Report Export Collapse

A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.

Which two actions should the team take to engage this new team member? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 424

Report Export Collapse

A company wants to increase the commercial value of one of its products in a highly competitive market. In order to do this, the company commissions a project to create a prototype. The team constructs the prototype incrementally.

Which action should the project manager take as a priority?

Become a Premium Member for full access
  Unlock Premium Member

Question 425

Report Export Collapse

During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 426

Report Export Collapse

A company's project management office (PMO) has started to implement iterative tools. A project manager is starting a new project and has identified an opportunity to use the iterative tools. One of the senior managers is concerned about this modified framework as it is fairly new to the company.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 427

Report Export Collapse

A project in the execution phase is behind schedule and is missing some materials. The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay. The project manager does not agree with the costs submitted by the contractor for the missing materials.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 428

Report Export Collapse

A project manager presented the project schedule to the mam stakeholders. They have requested that the project be completed two months earlier than the scheduled date.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 429

Report Export Collapse

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product. The project manager is afraid this might have a future impact on the quality and schedule, because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified?

(Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 430

Report Export Collapse

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline. There have been complaints from some stakeholders about some of the team members' performance. The project manager wants to understand the situation and provide feedback to the team as soon as possible.

What three actions should the project manager take to address this situation? (Choose three.)

Become a Premium Member for full access
  Unlock Premium Member