PMI PMP Practice Test - Questions Answers, Page 44

List of questions

Question 431

Report
Export
Collapse

An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services. The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch. There is a risk of a partner's system being unavailable which could impact the project negatively.

What key activity is needed to ensure the project's success?

Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result
Communicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result
Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution
Eliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution
Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue
Continuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue
Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities
Mitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities
Suggested answer: C
asked 23/09/2024
Rick James
43 questions

Question 432

Report
Export
Collapse

The CEO has authorized the development of a complex financial product for a company to provide greater future benefits. The budget has been acquired through financing with global investors who expect all risks to be identified as soon as possible.

What should the project manager use to identify the risks?

An analysis of shared risks between parties
An analysis of shared risks between parties
Strengths, weaknesses, opportunities, and threats (SWOT) analysis
Strengths, weaknesses, opportunities, and threats (SWOT) analysis
Expert judgment
Expert judgment
A risk value assessment
A risk value assessment
Suggested answer: B
asked 23/09/2024
Gaurav Nayak
43 questions

Question 433

Report
Export
Collapse

The sponsor is supportive in leveraging agile approaches. The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders.

What should the project manager do first?

Determine which agile software tools will be required to support agile delivery within the organization
Determine which agile software tools will be required to support agile delivery within the organization
Select a current predictive project, define the approach, and provide agile training to execute the remainder of the project
Select a current predictive project, define the approach, and provide agile training to execute the remainder of the project
Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted
Start with a pilot project of appropriate complexity, and provide agile training to those who are impacted
Determine how to transform the organization using agile techniques, including organizational training and communications
Determine how to transform the organization using agile techniques, including organizational training and communications
Suggested answer: D
asked 23/09/2024
Fahim Thanawala
43 questions

Question 434

Report
Export
Collapse

A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information.

What should the project manager do first to resolve this situation?

Update the issue log and escalate to the project sponsor
Update the issue log and escalate to the project sponsor
Identify the lack of information as a risk and update the risk register
Identify the lack of information as a risk and update the risk register
Schedule more frequent meetings with the technical manager
Schedule more frequent meetings with the technical manager
Review and update the stakeholder engagement plan
Review and update the stakeholder engagement plan
Suggested answer: D
asked 23/09/2024
Sathish M
48 questions

Question 435

Report
Export
Collapse

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version.

How can the project manager prevent this outcome in the new project?

Hire a team of external users to perform acceptance testing on the product
Hire a team of external users to perform acceptance testing on the product
Define a user focus group as external stakeholders with a high influence on outcomes
Define a user focus group as external stakeholders with a high influence on outcomes
Hire a consultant to perform a benefit analysis as an input to the project charter
Hire a consultant to perform a benefit analysis as an input to the project charter
Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS)
Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS)
Suggested answer: B
asked 23/09/2024
Shawn Sullivan
37 questions

Question 436

Report
Export
Collapse

In analyzing a project for monthly status reporting, the project manager notices that the schedule performance index (SPI) is 0,75 and the cost performance index (CPI) is 1,25. The project manager must provide the first project status review soon and wants to emphasize that the project is under control.

How should the project manager report the project status to key stakeholders?

Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results
Prepare a detailed presentation for stakeholders on earned value including how it is calculated and the project's current earned value results
Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget
Report that the project is behind schedule but that an additional experienced resource can be added to stay within schedule and maintain the budget
Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control
Perform a detailed root cause analysis utilizing a pareto chart and fishbone diagrams to demonstrate that the project is under control
Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away
Report that the project is not tracking as expected, but is still under control since the next project milestone is over a month away
Suggested answer: B
asked 23/09/2024
Fabio Valenti
38 questions

Question 437

Report
Export
Collapse

After a meeting with the customer, the project manager receives special recognition because the project is always on schedule. Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

Share the customer feedback with the project team
Share the customer feedback with the project team
Follow the meeting agenda and make a list of the next deliverables
Follow the meeting agenda and make a list of the next deliverables
Document this feedback in the meeting minutes
Document this feedback in the meeting minutes
Start planning how to improve the dates of next deliverables
Start planning how to improve the dates of next deliverables
Suggested answer: A
asked 23/09/2024
Jay Fletcher
49 questions

Question 438

Report
Export
Collapse

Team members are having a discussion with the project manager. In the last retrospective meeting, the team realized that the obsolete equipment could affect the next iteration of the project. The team recommends buying new equipment because it is critical to the success of the final deliverable.

What should the project manager do next?

Check the project budget to verify if there is enough contingency reserve
Check the project budget to verify if there is enough contingency reserve
Review the cost management plan to determine how to address this issue
Review the cost management plan to determine how to address this issue
Tell the team members that more equipment is not part of the project's scope
Tell the team members that more equipment is not part of the project's scope
Submit a change request to increase the budget and buy new equipment
Submit a change request to increase the budget and buy new equipment
Suggested answer: B
asked 23/09/2024
Aparecido Lemos
34 questions

Question 439

Report
Export
Collapse

A company's CEO has just returned from a conference on the use of artificial intelligence (AI) and would like the project manager to implement this technology in the organization.

What should the project manager do first?

Start developing a business case
Start developing a business case
Start a strength, weaknesses, opportunities and threats (SWOT)
Start a strength, weaknesses, opportunities and threats (SWOT)
Engage stakeholders and allocate resources
Engage stakeholders and allocate resources
Gather requirements from stakeholders
Gather requirements from stakeholders
Suggested answer: A

Explanation:

In order to do a SWOT analysis, you need an opportunity. Developing a business case is nothing but an opportunity and SWOT can follow it.

Explanation:

asked 23/09/2024
Alper Atar
43 questions

Question 440

Report
Export
Collapse

A project manager is leading a project with several stakeholders in other functional areas of the company. One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project.

What should the project manager have the project team update to ensure proper communications to stakeholders?

Project management plan
Project management plan
Stakeholder engagement plan
Stakeholder engagement plan
Stakeholder register
Stakeholder register
Communications management plan
Communications management plan
Suggested answer: B