ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 58

Add to Whishlist

List of questions

Question 571

Report Export Collapse

A project manager is leading a team that is geographically dispersed. The team needs to collaborate and finalize the monthly reports. Occasionally, meetings occur during the weekends due to the time differences. Team members have expressed that they do not want to work on the weekends.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 572

Report Export Collapse

A critical deliverable for the current iteration is giving the team difficulties. Functionality and quality issues are constantly emerging and delaying iteration progress.

The project manager listens to the team's concerns and discovered that the work is not being well coordinated among the team members.

Which two actions should the project manager take to handle this situation? (Choose two.)

Become a Premium Member for full access
  Unlock Premium Member

Question 573

Report Export Collapse

A project manager is managing a large project. During a review meeting, the project manager discovers that one of the team members who use to be a high performer was not able to complete their work on time.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 574

Report Export Collapse

An organization is initiating a project that will be using new technology. The complexity of the project requires excellent technical skills. After reviewing the proposed project management plan, the project sponsor asks for options to reduce the labor cost without introducing risk to the project delivery.

What should the project manager do first?

Become a Premium Member for full access
  Unlock Premium Member

Question 575

Report Export Collapse

A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Become a Premium Member for full access
  Unlock Premium Member

Question 576

Report Export Collapse

A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application.

Which estimation technique should the project manager recommend?

Become a Premium Member for full access
  Unlock Premium Member

Question 577

Report Export Collapse

A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 578

Report Export Collapse

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member

Question 579

Report Export Collapse

A construction company is executing a building contract that includes firm milestones for replacing certain components of the building. During execution, the client complains that the new components do not meet the requirements.

What should the project manager have done to prevent this from happening?

Become a Premium Member for full access
  Unlock Premium Member

Question 580

Report Export Collapse

An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.

What should the project manager do next?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions