A project manager is leading a meeting with key stakeholders, the project sponsor and the product owner to define the features that will be released after the next iteration. The purpose of the meeting is to review the product backlog prioritization, considering that during the past iteration some deliverables were not completed.

Which two items should be taken into account first to review and update the product backlog priorities during the meeting? (Choose two.)

A.
Complexity and the cost of development
A.
Complexity and the cost of development
Answers
B.
Industry trends and the technical approach
B.
Industry trends and the technical approach
Answers
C.
Cost of delaying some features against business value
C.
Cost of delaying some features against business value
Answers
D.
Reusing components from another product
D.
Reusing components from another product
Answers
E.
Length of time each feature has been on the backlog
E.
Length of time each feature has been on the backlog
Answers
Suggested answer: A, C

A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors.

Which two documents should the project manager update as soon as possible? (Choose two.)

A.
Issue log
A.
Issue log
Answers
B.
Risk register
B.
Risk register
Answers
C.
Stakeholder register
C.
Stakeholder register
Answers
D.
Change log
D.
Change log
Answers
E.
Backlog register
E.
Backlog register
Answers
Suggested answer: A, B

During an iteration of a project, a planned activity becomes more complex. The work should be delivered in the shortest time possible.

What approach should be used in this situation?

A.
The team facilitator gets support from external team members.
A.
The team facilitator gets support from external team members.
Answers
B.
The team members bring in a specialist to help them
B.
The team members bring in a specialist to help them
Answers
C.
The product owner moves it to the product backlog.
C.
The product owner moves it to the product backlog.
Answers
D.
The cross-functional team member work together to complete the activity
D.
The cross-functional team member work together to complete the activity
Answers
Suggested answer: D

A multinational company has a plan to expand their business into a new country where they currently have no presence. A project manager is assigned to initiate this project.

After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?

A.
Acquire project resources from the new country to mitigate the risk of uncertainty
A.
Acquire project resources from the new country to mitigate the risk of uncertainty
Answers
B.
Evaluate the environmental and regulatory factors and identify high-level risks and assumptions
B.
Evaluate the environmental and regulatory factors and identify high-level risks and assumptions
Answers
C.
Identify and monitor the risks closely since the company does not have lessons learned for this country
C.
Identify and monitor the risks closely since the company does not have lessons learned for this country
Answers
D.
Ensure that project sponsors are in agreement on the project deliverables and timeline during the project
D.
Ensure that project sponsors are in agreement on the project deliverables and timeline during the project
Answers
Suggested answer: B

A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.

How can the project manager promote empowerment and accountability among the team?

A.
Assign the tasks individually based on the role of the team member to ensure expertise on the subject.
A.
Assign the tasks individually based on the role of the team member to ensure expertise on the subject.
Answers
B.
Encourage and assign the team to perform demos of their products or software with the customers
B.
Encourage and assign the team to perform demos of their products or software with the customers
Answers
C.
Give the team autonomy to make their own decisions on how to perform the tasks
C.
Give the team autonomy to make their own decisions on how to perform the tasks
Answers
D.
Encourage the team to keep the product owner involved when choosing ways to resolve the given task
D.
Encourage the team to keep the product owner involved when choosing ways to resolve the given task
Answers
Suggested answer: C

A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task.

What should the project manager do?

A.
Ask the team member to follow the approved communications management plan to communicate their issue
A.
Ask the team member to follow the approved communications management plan to communicate their issue
Answers
B.
Schedule a meeting with the concerned team member to review and update the issue log together
B.
Schedule a meeting with the concerned team member to review and update the issue log together
Answers
C.
Review the risk register with the team member to find the proper response action for this issue
C.
Review the risk register with the team member to find the proper response action for this issue
Answers
D.
Ask the team member to raise a change request to assess the issue in detail
D.
Ask the team member to raise a change request to assess the issue in detail
Answers
Suggested answer: B

During the last sprint review the product owner stated that the product does not deliver any value.

The project manager believes that the product meets all the provided specifications. The team is confused by the product owner's statement.

What should the project manager do when using a hybrid approach?

A.
Escalate the matter to the executive board so they can decide on next steps
A.
Escalate the matter to the executive board so they can decide on next steps
Answers
B.
Prioritize the project backlog and ask the development team to fix the issues
B.
Prioritize the project backlog and ask the development team to fix the issues
Answers
C.
Review the project's benefits management plan with the product owner
C.
Review the project's benefits management plan with the product owner
Answers
D.
Ask the product owner to terminate the project as it is no longer aligned to the expected benefits
D.
Ask the product owner to terminate the project as it is no longer aligned to the expected benefits
Answers
Suggested answer: C

A geographically distributed project team has development issues between the collocated and virtual teams causing productivity to decrease.

What should the project manager do to address this issue?

A.
Force the team members to work from one location
A.
Force the team members to work from one location
Answers
B.
Develop protocols for resolving conflicts between team members
B.
Develop protocols for resolving conflicts between team members
Answers
C.
Obtain special expertise to advise the team members
C.
Obtain special expertise to advise the team members
Answers
D.
Set up face-to-face meetings with project team members
D.
Set up face-to-face meetings with project team members
Answers
Suggested answer: B

A Scrum team has committed to delivering a specific capability in their first release. Multiple operational issues have prevented the developer from delivering key capabilities. The technical lead has also given notice that they are resigning from the company.

What should the project manager have the Scrum team do to recover from these issues?

A.
Review constraints in the ongoing sprint planning and evaluate options for the release plan
A.
Review constraints in the ongoing sprint planning and evaluate options for the release plan
Answers
B.
Stop the sprint and replan and prioritize the backlog to reduce resource levels
B.
Stop the sprint and replan and prioritize the backlog to reduce resource levels
Answers
C.
Consult the resource management plan for an appropriate response
C.
Consult the resource management plan for an appropriate response
Answers
D.
Continue with existing sprint plans to ensure some of the scope will be delivered
D.
Continue with existing sprint plans to ensure some of the scope will be delivered
Answers
Suggested answer: A

A project manager is leading a large-scale project that involves 70 stakeholders. The project manager has heard various comments and expectations from the customers, some of which are contradictory. Consequently, some requirements are not clear.

What should the project manager do to build consensus regarding the requirements?

A.
Escalate the issue to the management team for their review and guidance
A.
Escalate the issue to the management team for their review and guidance
Answers
B.
Create a survey template to collect feedback from stakeholders to reach an agreement
B.
Create a survey template to collect feedback from stakeholders to reach an agreement
Answers
C.
Organize a face-to-face meeting with all stakeholders to understand their interests and concerns
C.
Organize a face-to-face meeting with all stakeholders to understand their interests and concerns
Answers
D.
Leverage expert judgment to determine the requirements that should be considered
D.
Leverage expert judgment to determine the requirements that should be considered
Answers
Suggested answer: C