PMI PMP Practice Test - Questions Answers, Page 57
List of questions
Related questions
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project.
What should the project manager do first to determine a governance approach for the project?
A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization. The project team is experiencing low morale and poor teamwork.
What should the project manager do to improve morale?
A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
A project manager and protect team are developing a strategic approach to engage the internal and external stakeholders.
Which approach should be followed?
A distributed protect team wants to use the common ground principle to ensure that they have a common understanding of the scope. The team asks the protect lead to set up a workshop.
What should the project lead do?
A client mentioned that in the past 2 months, they have not been invoiced for completed work.
The client has communicated that they will release the funds for other activities it the invoices are not sent.
What should the project manager do next?
Midway through the execution of an agile protect there is a shift in the strategic objectives at the organization level to promote digital transformation.
What should the project manager do next?
A project manager is assigned to a project that will improve the business operations for a trading firm. The project team has just completed the discovery phase and needs to make a presentation to the business team in 4 weeks to showcase the feasibility of the solution.
How should the project manager advise the team to proceed?
Project reviews are done regularly in a project. The team has encountered a critical technical issue that will be discussed in the next project review.
Who should the project manager invite to the review for an effective decision on the way forward?
A project manager is initiating an agile project for which some external components will be delivered by vendors. One of the vendors, however, will be unable to deliver its component in an incremental, collaborative way.
How should the project manager handle this situation?
Question