ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 80

Add to Whishlist

List of questions

Question 791

Report Export Collapse

A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory.

How should the project manager support their claim to the vendor?

Become a Premium Member for full access
  Unlock Premium Member

Question 792

Report Export Collapse

A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?

Become a Premium Member for full access
  Unlock Premium Member

Question 793

Report Export Collapse

A project manager who is working with a virtual team needs to mentor an entry-level colleague.

This team member informs the project manager that they feel demotivated and excluded from the team. What should the project manager do first to solve the situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 794

Report Export Collapse

A project manager is managing the development of a dental wire bending machine. The machine is compatible with the three most popular dental wires in the market which covers 90% of the market. The prototype is now under testing for certification. The manufacturer of one of the three wires announced they will be producing a different wire mat will be incompatible with the machine. This will result in a 25% loss of market coverage from the initially predicted 90%coverage. What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 795

Report Export Collapse

A project manager is leading a team of diverse individuals of all ages. The working hours for the project were set at the beginning of the project, and all team members agreed to the hours.

However, later in the project, one of the team members informed the project manager that the previously agreed upon hours no longer work due to the team member's personal commitments.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 796

Report Export Collapse

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.

What should the project manager do?

Become a Premium Member for full access
  Unlock Premium Member

Question 797

Report Export Collapse

A project manager has just been hired to lead a project team in a hybrid environment. The team is working on a group of critical projects.

What should the project manager do to ensure the right environment and authority are in place to effectively deliver the projects?

Become a Premium Member for full access
  Unlock Premium Member

Question 798

Report Export Collapse

A building management system (BMS) project is in its commissioning phase and handover to the operations team will commence soon. However, the project manager noted that both the project and operation teams are not able to properly operate the BMS. As a result, there is an increased risk of the project schedule being delayed.

What should the project manager have done to avoid this situation?

Become a Premium Member for full access
  Unlock Premium Member

Question 799

Report Export Collapse

A team working on a close deployment waits to receive critical information from the customer.

The customer keeps postponing sending the information which is delaying the deployment.

What should the project manager have done to prevent the delay?

Become a Premium Member for full access
  Unlock Premium Member

Question 800

Report Export Collapse

A project manager is assigned to a new project that will launch the digital version of a current product. Even though the product is well known, the vision for its digital version is not clear to the stakeholders.

What should the project manager do to increase value delivery?

Become a Premium Member for full access
  Unlock Premium Member
Total 1.477 questions
Go to page: of 148
Search

Related questions