Question 811

The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies, and the project manager needs the director's support as the marketing director is a key stakeholder.
What should the project manager do to obtain the support?
Question 812

A project manager is appointed to simultaneously deploy a new solution to branches located in different countries. Deployment teams in each country will integrate and deploy the solution. The project manager discovers that the deployment teams each encounter similar issues. However, each team addresses the issues separately.
What should the project manager do to help ensure more collaboration between the teams?
Question 813

A company has a lot of experience with predictive projects. The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project. After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.
What should the project manager do?
Question 814

A project manager receives a voicemail from a business analyst on the project team. The business analyst indicates that an internal stakeholder is upset that they were not included before the project began. The stakeholder is asking for an addition to the requirements traceability matrix.
What should the project manager do to improve the stakeholder relationship?
Question 815

Development team members are located in three different time zones. It is difficult to find a suitable time to hold the daily standup for all team members.
What should the project manager do?
Question 816

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation.
How should the project manager respond?
A single team member wouldn't develop risk strategies, that will likely either be up to an entire team or at minimum, the PM.
Explanation:
Question 817

A company is implementing a new system. The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies. The product owner is confused as to how to start delivering the functionalities required.
How should the project manager assist the product owner?
Question 818

An agile project is in its eighth iteration out of 16. After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply.
Which two actions should the project manager take? (Choose two.)
Question 819

An agile leader is working on a complex project that is entering the final phase where solutions from different vendors are being integrated. This is the most critical delivery stage for the project How should the agile leader ensure successful delivery?
Question 820

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?
Question