ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 84

List of questions

Question 831

Report Export Collapse

A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.

What does this value mean for the project?

The project is earning less value than was planned
The project is earning less value than was planned
The project has started exceeding the planned cost
The project has started exceeding the planned cost
The project has earned more value than planned
The project has earned more value than planned
The project is close to exceeding the planned cost
The project is close to exceeding the planned cost
Suggested answer: B
asked 23/09/2024
Assane SENE
44 questions

Question 832

Report Export Collapse

A customer complains that the user stories released so far contain too much jargon and do not reflect the expectations of the product.

What should the project manager do next?

Rewrite the stories to include the technical vision of the product
Rewrite the stories to include the technical vision of the product
Ask the senior developer to rewrite all the stories
Ask the senior developer to rewrite all the stories
Engage with the customer and rewrite all the stories
Engage with the customer and rewrite all the stories
Request approval from the company director to conduct training for the team
Request approval from the company director to conduct training for the team
Suggested answer: C
asked 23/09/2024
Richard Villanueva
39 questions

Question 833

Report Export Collapse

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Add 4 additional weeks to the schedule and request additional resources.
Add 4 additional weeks to the schedule and request additional resources.
Ask the sponsor to obtain a special work permit to continue work.
Ask the sponsor to obtain a special work permit to continue work.
Crash the resource management plan to keep the schedule on track.
Crash the resource management plan to keep the schedule on track.
Review the project management plan to see the impact of the possible delay.
Review the project management plan to see the impact of the possible delay.
Suggested answer: D
asked 23/09/2024
Nigel Choji
51 questions

Question 834

Report Export Collapse

During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.

Which project document should the project manager review in order to determine the reason for this issue?

Requirements traceability matrix
Requirements traceability matrix
Issue log
Issue log
Stakeholder register
Stakeholder register
Stakeholder engagement assessment matrix
Stakeholder engagement assessment matrix
Suggested answer: D
asked 23/09/2024
PRABHAT VAIBHAV
34 questions

Question 835

Report Export Collapse

A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team was average.

What should the project manager do to help the new compliance specialist improve?

Coordinate a one-to-one meeting with the specialist to assess the situation
Coordinate a one-to-one meeting with the specialist to assess the situation
Escalate this situation to the manager of the area for a possible solution
Escalate this situation to the manager of the area for a possible solution
Provide time for the specialist to adjust to the pace of the project
Provide time for the specialist to adjust to the pace of the project
Contact the human resources (HR) manager about the team's feedback
Contact the human resources (HR) manager about the team's feedback
Suggested answer: A
asked 23/09/2024
Gina Diaz
38 questions

Question 836

Report Export Collapse

A company has selected a cross-functional team to develop an innovative digital product to drive the digital transformation project for the business.

What should the project manager do to ensure business value is delivered early?

Create robust incentives to the team members to encourage speedy delivery
Create robust incentives to the team members to encourage speedy delivery
Create a detailed project plan and escalate delays to the functional managers
Create a detailed project plan and escalate delays to the functional managers
Break down the deliverables into sprints and deliver value incrementally
Break down the deliverables into sprints and deliver value incrementally
Fast track the project and monitor tasks closely to ensure timely delivery
Fast track the project and monitor tasks closely to ensure timely delivery
Suggested answer: C
asked 23/09/2024
Jeffrey Cayao
42 questions

Question 837

Report Export Collapse

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.
Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.
Ask team members to research and collect data about the best features offered by similar products in the market.
Ask team members to research and collect data about the best features offered by similar products in the market.
Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.
Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.
Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.
Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.
Suggested answer: B
asked 23/09/2024
Musoke Kamuzze
34 questions

Question 838

Report Export Collapse

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

Establish a probability and impact matrix and plan response criteria.
Establish a probability and impact matrix and plan response criteria.
Disregard the situation since it is not hindering the project deliverables.
Disregard the situation since it is not hindering the project deliverables.
Develop a joint policy among the various organizations.
Develop a joint policy among the various organizations.
Escalate the issue to the project sponsor and seek their guidance.
Escalate the issue to the project sponsor and seek their guidance.
Suggested answer: B
asked 23/09/2024
Mounir Mrabet
47 questions

Question 839

Report Export Collapse

A project manager is leading a project that needs to be deployed quickly to the market. An influential stakeholder does not believe that the project management processes bring business value.

What can the project manager do to gain the support of the stakeholder?

Ask the stakeholder for a meeting to review the project's charter and project management plan.
Ask the stakeholder for a meeting to review the project's charter and project management plan.
Disregard the stakeholder's concerns and continue following the project management plan to execute the project.
Disregard the stakeholder's concerns and continue following the project management plan to execute the project.
Hold a training workshop to educate the stakeholder about project management best practices.
Hold a training workshop to educate the stakeholder about project management best practices.
Clarify the project roles and responsibilities, and share the purpose to gain the stakeholder's buyin.
Clarify the project roles and responsibilities, and share the purpose to gain the stakeholder's buyin.
Suggested answer: D
asked 23/09/2024
Dustin Sickle
35 questions

Question 840

Report Export Collapse

A team is finishing the third release to present to the stakeholder as part of a demonstration. The company that subcontracts the developers has communicated that there is a cash flow problem and the company will not be able to provide the same resources for the next iterations.

What should the project manager do next?

Create a risk register to track the risks and request additional budget.
Create a risk register to track the risks and request additional budget.
Analyze the impact against the release plan if the blocker is not addressed.
Analyze the impact against the release plan if the blocker is not addressed.
Work with the project owner to prioritize the product backlog.
Work with the project owner to prioritize the product backlog.
Escalate the situation to the project sponsor for a possible resolution.
Escalate the situation to the project sponsor for a possible resolution.
Suggested answer: B
asked 23/09/2024
Pawel Lenart
39 questions
Total 1.477 questions
Go to page: of 148
Search

Related questions