Question 689 - PMP discussion
A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.
What should the project manager do next?
A.
Give the senior manager access to the product backlog.
B.
Organize a review of the kanban board with the manager.
C.
Contact the senior manager and discuss their needs.
D.
Modify the PMO template to include the information.