PMI PMP Practice Test - Questions Answers, Page 81
List of questions
Question 801

A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?
Question 802

A project's customer is furious. When the customer arrived at the project site, they discovered that one of their requirements was not met.
What should the project manager do?
Question 803

A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.
What should the project manager do?
Question 804

A new law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?
Question 805

A controller proposed a budget reduction for projects because the majority of implemented solutions resulted in little returns on investment (ROI) or operational improvements. The project manager objected and presented project assets showing all solutions having been demonstrated, accepted, and delivered within the relevant framework constraints. The project manager suggested that the issues may stem from the project evaluation and selection processes.
What was the project manager demonstrating?
Question 806

An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures.
What should the project manager do to help avoid this situation in the future?
Question 807

A project manager is managing a complex research project with a high level of uncertainty. A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
Explanation:
Paired Work will improve quality, and the question is asking about a method to measure the quality.
Explanation:
Question 808

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements.
How should the project manager address this situation?
Question 809

A new project manager learns the work assigned to the team has already been decomposed to its lowest level. The project manager reviews the work and feels some additional, useful information is missing.
What should the project manager review?
Explanation:
A WBS dictionary is where the details of the tasks, activities, and deliverables of the work breakdown structure are located. The content includes whatever milestones are related, the project scope and in some instances dates, resources, cost and quantity.
Explanation:
Question 810

The programming activities of a project were planned to last 35 days per module, but the programming of the first module has taken 45 days.
What should the project manager do?
Question