ExamGecko
Home / PMI / PMP / List of questions
Ask Question

PMI PMP Practice Test - Questions Answers, Page 7

Add to Whishlist

List of questions

Question 61

Report Export Collapse

A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements.

What should the project manager do?

Put into place a project governance model in line with the requirements
Put into place a project governance model in line with the requirements
Replicate the organizational governance to the project governance
Replicate the organizational governance to the project governance
Create an organizational project management governance
Create an organizational project management governance
Ask the organization to create a project portfolio governance
Ask the organization to create a project portfolio governance
Suggested answer: A
asked 23/09/2024
Herr Eylem Bulut
52 questions

Question 62

Report Export Collapse

A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.

What should the project manager do?

Explain the third-party supplier situation to the client and request payment.
Explain the third-party supplier situation to the client and request payment.
Inform the client that the project must be delayed until payment is received.
Inform the client that the project must be delayed until payment is received.
Reassign resources from other projects to pay the third-party supplier.
Reassign resources from other projects to pay the third-party supplier.
Process a bank loan to pay the payroll of the third-party supplier.
Process a bank loan to pay the payroll of the third-party supplier.
Suggested answer: A
asked 23/09/2024
Julius Nammeh
50 questions

Question 63

Report Export Collapse

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders.

What should the project manager do to get this information?

Identify each stakeholder's motivations from the business case.
Identify each stakeholder's motivations from the business case.
Request stakeholders articulate their motivations at the kick-off meeting.
Request stakeholders articulate their motivations at the kick-off meeting.
Email project objectives to all stakeholders and ask for endorsement.
Email project objectives to all stakeholders and ask for endorsement.
Organize a one-on-one conversation with each stakeholder.
Organize a one-on-one conversation with each stakeholder.
Suggested answer: D
asked 23/09/2024
Jaime GONCALVES
49 questions

Question 64

Report Export Collapse

During a project's initiation phase, a lessons learned sharing session was held with the team from another project. Low construction productivity was discussed as a potential delay to project completion.

What should the project manager do next?

Discuss this issue with the project sponsor to request additional funding to implement mitigation
Discuss this issue with the project sponsor to request additional funding to implement mitigation
Prequalify contractors with proven track records to eliminate productivity concerns
Prequalify contractors with proven track records to eliminate productivity concerns
Add construction productivity to the risk register and develop a mitigation strategy for site execution
Add construction productivity to the risk register and develop a mitigation strategy for site execution
Hire a construction management consultant to develop a comprehensive site execution plan
Hire a construction management consultant to develop a comprehensive site execution plan
Suggested answer: C
Explanation:

The learning from prior project was about construction productivity. So in order to prevent it happen in a new project, it has to monitored with a mitigation plan.

Explanation:

asked 23/09/2024
Victor Armando Sánchez
43 questions

Question 65

Report Export Collapse

A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact project implementation.

What should the project manager do next?

Assign an additional resource to help the team member with the tasks
Assign an additional resource to help the team member with the tasks
Ask the team member's functional manager if there are any known issues
Ask the team member's functional manager if there are any known issues
Convene a team meeting to encourage and motivate the entire team
Convene a team meeting to encourage and motivate the entire team
Meet with the team member to understand their concerns and/or issues
Meet with the team member to understand their concerns and/or issues
Suggested answer: D
asked 23/09/2024
Ismaiel Al-Mufleh
50 questions

Question 66

Report Export Collapse

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?

Engage the agile resources through video conferencing on a daily basis
Engage the agile resources through video conferencing on a daily basis
Advise the sponsor that the project will be delayed as agile training will be required
Advise the sponsor that the project will be delayed as agile training will be required
Request a budget extension to get local resources experienced in agile
Request a budget extension to get local resources experienced in agile
Plan to have the agile resources temporarily relocate to the project manager's location
Plan to have the agile resources temporarily relocate to the project manager's location
Suggested answer: A
asked 23/09/2024
Arun Pandian
47 questions

Question 67

Report Export Collapse

An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.

How should the facilitator proceed?

Set up a lessons learned session from a similar project.
Set up a lessons learned session from a similar project.
Hold a team charter discussion.
Hold a team charter discussion.
Schedule a release planning session.
Schedule a release planning session.
Conduct a product roadmap session with the team.
Conduct a product roadmap session with the team.
Suggested answer: B
asked 23/09/2024
MARCONDES SANTOS
38 questions

Question 68

Report Export Collapse

A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months, but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities planned for that date were fulfilled.

How should the project manager inform the stakeholders of the project's progress?

Complete the outstanding functionalities before informing the sponsor of the project progress
Complete the outstanding functionalities before informing the sponsor of the project progress
Communicate the benefit expectations and the action plan for the pending functionalities
Communicate the benefit expectations and the action plan for the pending functionalities
Send an email with the monthly project progress to all relevant stakeholders
Send an email with the monthly project progress to all relevant stakeholders
Report that the project has not fulfilled all the expected functionalities
Report that the project has not fulfilled all the expected functionalities
Suggested answer: B
asked 23/09/2024
Artem Masin
30 questions

Question 69

Report Export Collapse

A project manager is working on the delivery of a solution that needs to be deployed to the public quickly. The project team is experienced, the stakeholders are supporting the delivery, and the customer is cooperating.

What strategy should the project manager use to ensure on-time delivery of the solution?

Meet with the customer to agree on the components of the solution and the priorities
Meet with the customer to agree on the components of the solution and the priorities
Ask the sponsor for support regarding the allocation of additional resources to finish on time
Ask the sponsor for support regarding the allocation of additional resources to finish on time
Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible
Have a high-level plan for incremental deliveries and get the customer's feedback as early as possible
Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources
Have a detailed plan of all milestones, deliverables, functionalities, and allocation of resources
Suggested answer: C
asked 23/09/2024
Oleksandr Kondratchuk
38 questions

Question 70

Report Export Collapse

There is frequent conflict between two project team members working on a project. This has caused a negative impact on the project.

How should the project manager handle this situation?

Counsel both team members and caution them with a final warning.
Counsel both team members and caution them with a final warning.
Relocate the two project team members into different project teams.
Relocate the two project team members into different project teams.
Escalate the issue to the human resources (HR) manager before a larger problem develops.
Escalate the issue to the human resources (HR) manager before a larger problem develops.
Help cultivate self-awareness between the two team members through emotional intelligence (EI).
Help cultivate self-awareness between the two team members through emotional intelligence (EI).
Suggested answer: D
asked 23/09/2024
B Erol
63 questions
Total 1.477 questions
Go to page: of 148
Search

Related questions