PMI PMP Practice Test - Questions Answers, Page 88
List of questions
Question 871
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A team is about to close a deployment and is waiting to receive critical information from the customer. The customer continues to postpone sending information, which is consequently delaying the deployment.
What should the project manager have done to prevent the delay?
Question 872
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project defined to be executed in four months is divided into eight iterations. During its first retrospective, the team realizes that only one member has experience doing a key project requirement.
What should the project manager do?
Question 873
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager who is providing development support for a product notices some of their longstanding customers moving to a competitor because of improved value being delivered from their product. What should the project manager do first?
Question 874
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
Question 875
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager and project team developing a new product are discussing which work methods and tools to use to build the deliverable. What should the result of this discussion be?
Question 876
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder in order to provide necessary resources. However, the stakeholder is refusing to get involved because the stakeholder thinks that there is no benefit in using the project deliverable.
What should the project manager do to resolve this?
Question 877
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
While working on a proposal for a national-level solution, a new project manager finds that the proposal is asking for compliance from various organizations and policies. The project manager understands that while several compliances are in place, some of the specific regulatory needs for this project are not in place. Senior management advised the project manager to overlook these compliance problems, because they will be ready when that stage of the project is reached, and to continue building the proposal.
What should the project manager do first?
Question 878
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience. The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
Question 879
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint, the project manager notices that the team is not working as a cohesive unit.
Which two rules are appropriate for the project manager to instill in the team? (Choose two.)
Question 880
![Export Export](https://examgecko.com/assets/images/icon-download-24.png)
A project manager is working on a large project with a very difficult client. During the course of the project, the project manager realizes that if the project team had a little more time and funding to make some minor changes, the client could realize the benefits of 25% of the project outcomes early.
How should the project manager approach this?
Question