An agile team is working on a two-week sprint to deliver business value. About one week after the sprint starts, the product owner realizes that a regulatory compliance requirement was missed.

The product owner reminds the team that this requirement must be completed in the current sprint or the organization will face a penalty.

What should the project manager do to mitigate this risk?

A.
Review the issue with the project sponsor and ask for more time to complete this requirement.
Answers
A.
Review the issue with the project sponsor and ask for more time to complete this requirement.
B.
Complete an impact analysis as the scope of the sprint backlog cannot be changed after the sprint has started.
Answers
B.
Complete an impact analysis as the scope of the sprint backlog cannot be changed after the sprint has started.
C.
Include the compliance user story in the next sprint as the team is fully occupied with the current sprint.
Answers
C.
Include the compliance user story in the next sprint as the team is fully occupied with the current sprint.
D.
Request the team to add the user story to the current sprint and let them work on it.
Answers
D.
Request the team to add the user story to the current sprint and let them work on it.
Suggested answer: D